Project Information
The installation of the electro-mechanical system for the Mini Hydro Power Plant (MHPP) Cibanteng, with a capacity of 1x4.5MW, is located in Cianjur, West Java. This project aims to enhance the region's energy supply through renewable sources. The system installation is critical for ensuring efficient energy production and long-term operational stability of the power plant.
- Client: PT Prima Atrya Energi
- Our Role: Engineering, Procurement, and Construction (EPC) contractor for the electro-mechanical system.
- Date: 2021
- Category: Renewable Energy, Hydro Power
Scope of Work
Design and Engineering
Development of detailed engineering designs for the electro-mechanical systems, ensuring compliance with industry standards and project specifications.
Equipment Supply and Installation
Procurement and installation of critical components, including turbines, generators, and control systems, ensuring seamless integration with the existing infrastructure.
Testing and Commissioning
Comprehensive testing and commissioning of the electro-mechanical systems to ensure optimal performance and reliability of the MHPP.